Press release
Bucharest, July 12th 2021
SN Nuclearelectrica SA announces that Unit 2 of Cernavoda NPP was reconnected to the National Power Grid during the evening of July 12th 2021.
Cernavoda NPP Unit 2 automatically disconnected from the National Power Grid in the afternoon of July 10th 2021 following a disfunction in the classical part of the unit, without any impact on the nuclear part.
The automatic disconnection of Unit 2, as well as the remediation works had no impact on the nuclear safety of the reactor, personnel, population and environment.
Cosmin Ghita
CEO