Bucharest, July 30th 2021
Press release
Cernavoda NPP Unit 2 reconnection to the National Power Grid
SN Nuclearelectrica SA announces that Unit 2 of Cernavoda NPP was reconnected to the National Power Grid during in the evening of July 30th, 2021.
Cernavoda NPP Unit 2 automatically disconnected from the National Power Grid on the evening of July 28, 2021, following a transient in the energy system which affected the classical part of the unit, without affecting the nuclear safety functions of the reactor.
The automatic disconnection of Unit 2, as well as the remediation works had no impact on the nuclear safety of the reactor, personnel, population and environment.
Cosmin Ghita
CEO