Press release
Societatea Nationala Nuclearelectrica S.A. (“SNN”) that Cernavoda NPP Unit 2 will enter the planned shutdown program, starting with May 8th, 2015. The Unit will be desynchronized from the National Power Grid during the night of 8th to the 9th of May, at 00:00 hours.
The planned shutdowns of Cernavoda NPP Units 1 and 2 are part of the maintenance program and are performed once every two years for each unit.
During the planned outage, the following activities will be carried out within the following programs:
- Preventive and corrective maintenance program;
- Mandatory inspections program;
- Mandatory testing program, in compliance with CNCAN’s requirements, that can be performed only during an outage period;
- Project changes implementation program on certain systems/equipment/components.
The works will be performed under safe conditions for the plant personnel, public and environment in accordance with the approved procedures applied by the Cernavoda Nuclear Power Plant.
Daniela Lulache
CEO