Restart of Cernavoda NPP Unit 2

7 Jun

Restart of Cernavoda NPP Unit 2

Nuclearelectrica announces the completion of the biannual planned shutdown period of Cernavoda NPP Unit 2 with great success.

On June the 1st 2011, Unit 2 has been synchronization with the National Power Grid and it reached full power on June the 2nd 2011.
During the Planned Shutdown, which started on May 7th 2011, the following program activities were performed at the station:
– The program for mandatory inspections
– The program for preventive and corrective maintenance
– The mandatory testing program during Planned Shutdown, according to the regulations of CNCAN, which can be performed during reactor shutdown
– The program for implementation of project alterations on certain systems/equipments/components.

The activities were carried out ensuring complete safety for the personnel, the population and the environment, according to the procedures approved and in use at Cernavoda NPP.