Press release
Bucharest, 3 November 2018
SN Nuclearelectrica SA (“SNN”) announces that Cernavoda NPP Unit 1 is operating at full power, as the repair works on the tank related to the turbogenerator (the classical part of the power plant) have been completed.
We remind the fact that the repair works could only be performed with Unit 1 reactor at a reduced power.
The controlled power reduction and the completion of the works were performed under full nuclear safety conditions in compliance with the specific procedures of the power plant.
Cosmin Ghita
CEO